Kamarajar Port’s second terminal would add 20 lakh TEUs in two phases

2 minutes

The new terminal’s first phase would exceed the existing terminal’s capacity. The opening timeline starts with a concession award, not Cabinet approval.

Kamarajar Port plans a second container terminal. PLANNED ANNUAL CAPACITY: 20 LAKH TEUs. 11 lakh in phase one. 9 lakh in phase two. Capacity is not cargo already handled.

Kamarajar Port, north of Chennai, handled roughly 7 lakh twenty-foot equivalent units of container traffic in FY2025–26. Its existing terminal can handle 8 lakh a year. Now the government has approved a second terminal that would add 20 lakh of annual capacity, but not all at once.

A twenty-foot equivalent unit, or TEU, measures container capacity in units of a standard 20-foot box. A 40-foot container counts as two TEUs. Both terminals’ numbers use the same unit; one figure is what moved last year, the others are how much the terminals are designed to handle.

The first phase would add more capacity than the existing terminal has

The first phase is designed for 11 lakh TEUs a year, with a further 9 lakh in the second. The government’s schedule targets first-phase operations in month 25 and full operations in month 49, both measured from the award of the concession. The 25 November approval is not that award. The proposal calls for the relevant environmental and other clearances before bids are due.

The port and the private operator have different bills

The private operator selected through bidding is expected to finance the estimated ₹4,288 crore terminal component, including GST, and recover its investment through user charges under the concession. The publicly owned port would separately bear an estimated ₹450 crore for dredging, the work that deepens the water for ships. The proposed concession runs 40 years, including construction.

A deeper berth makes direct ship calls possible, not inevitable

The proposed terminal is designed for an 18-metre draft and much larger container vessels. A direct call could save some exporters a transfer through another hub. But shipping lines still need enough cargo and a schedule that works for their network. For businesses around Chennai and Ennore, the next milestones to watch are clearances and an awarded concession. After opening, the useful measures will be direct services and actual cargo handled, not just the rated capacity.