Sandur plans ₹280 crore iron ore upgrading plant

2 minutes

The Sandur Manganese & Iron Ores Limited plans to invest approximately ₹280 crore in its first in-mine iron ore upgrading plant at Deogiri in Karnataka. In a November 19 exchange filing, the company said the first unit was about 25% complete and targeted commissioning in August 2027. The project’s capacity figures describe different stages of…

Sandur plans ₹280 crore upgrading plant. Input capacity is not upgraded output.

The Sandur Manganese & Iron Ores Limited plans to invest approximately ₹280 crore in its first in-mine iron ore upgrading plant at Deogiri in Karnataka. In a November 19 exchange filing, the company said the first unit was about 25% complete and targeted commissioning in August 2027.

The project’s capacity figures describe different stages of the process. The first unit is designed to process 3.5 million tonnes of ore a year. Sandur expects initial upgraded output of 1.0–1.2 million tonnes annually, with potential output of up to 1.7 million tonnes. The input figure is therefore not a forecast of saleable upgraded output.

The process, known as beneficiation, is intended to turn lower-grade ore into a higher-grade concentrate. Sandur says the plant is designed to raise iron content from about 50% to more than 60%, making the material suitable for pellet manufacturing. Those are design and performance expectations, not results from an operating plant.

Ore would come from the company’s KTIO mines and some from its Deogiri mines. Locating processing at the mine is expected to reduce the movement of waste-bearing ore. The release also describes expected benefits for tailings management, but does not quantify achieved transport savings or environmental results.

Sandur reports that civil works and structural fabrication are progressing and orders for long-lead equipment have been placed. Funding is expected to combine debt and internal accruals. The wider development plan envisages two 3.5-million-tonne units, but the stated completion progress and August 2027 commissioning target relate to the first unit.

The commercial proposition is better-quality material rather than simply more tonnes. Management expects improved marketability and revenue realization, and says the concentrate could also support iron-making within the group. These remain expectations: the disclosure does not establish a realized selling-price premium, operating margin or return on the investment.

For readers tracking the project, the next meaningful milestones are construction completion, commissioning and evidence of sustained upgraded output. A processing capacity, an initial output target and a potential output ceiling should not be added together or treated as interchangeable measures.

Source: Sandur’s November 19, 2026 exchange-filed release. Construction progress and future targets are attributed to the company.