Adani’s Bihar grid award carries a ₹500 crore annual tariff after commissioning

1 minute

Adani Energy Solutions says its Bihar grid award carries about ₹500 crore a year after commissioning. The tariff is not the project’s construction cost.

Illustrated transmission towers with the Bihar grid award’s annual tariff

Adani Energy Solutions said on 19 November that it had won a Bihar transmission project carrying an annual tariff of about ₹500 crore once commissioned. The figure is the annual tariff quoted for the grid project, not a construction budget or money the company is earning today.

What the bid price measures

The company won the project through tariff-based competitive bidding. The number it disclosed is therefore an annual figure tied to the project entering service, rather than a one-time order value. The announcement did not disclose the capital cost, so the annual tariff alone does not tell readers how much the company will spend building the network or what return it expects.

The grid and power plant are separate projects

The network is intended to carry electricity from Adani Power’s separate planned 2,400 MW thermal station at Pirpainti. The 2,400 MW refers to the generating station, not the transmission operator’s generating capacity. Adani Energy Solutions said the network will span 881 circuit kilometres, a measure of the length of the individual electrical circuits, not the distance the route covers on a map.

REC’s August exchange filing said Bihar had assigned its subsidiary REC Power Development and Consultancy to run the bidding process and that Vikramshila Power Transmission Ltd had been incorporated for the project. Adani Energy Solutions says the project will be implemented through that company.

When the tariff would start

Adani Energy Solutions is targeting commissioning in the final quarter of 2028. That is the company’s schedule, not a commissioning date already achieved. The next milestone for the tariff is the network entering service, not the announcement of the winning bid.