BPCL’s board backs its Andhra refinery. What still needs approval?

2 minutes

BPCL estimates the Ramayapatnam complex will cost ₹1,26,656 crore. Its equity contribution, lender arrangements and July 2032 target are separate decisions.

BPCL estimates ₹1,26,656 crore for the Ramayapatnam complex, plus or minus 20%. Its separate equity ceiling of ₹44,330 crore still needs approvals.

BPCL’s board has approved a new refinery and petrochemical complex at Ramayapatnam in Andhra Pradesh. The company estimates it will cost ₹1,26,656 crore. That is the estimated cost of building the entire complex, not the amount BPCL has already spent or committed to paying entirely from its own funds.

What the board approved

In its 28 November exchange filing, BPCL said the project will go through a wholly owned subsidiary, subject to applicable government and regulatory approvals. It put a margin of plus or minus 20% around the capital cost estimate and named July 2032 as the estimated start of commercial operations. Neither the cost nor the date is fixed.

The board separately approved up to ₹44,330 crore of equity for the subsidiary, including up to ₹4,900 crore approved earlier. That ceiling is about 35% of the headline project estimate. The equity needs Cabinet Committee on Economic Affairs and other applicable approvals, and BPCL says the equity and debt arrangements are still being finalised with lenders. Subtracting the two headline numbers does not produce a confirmed borrowing figure.

Why 10.5 million tonnes is not all crude

The proposed refinery would process 9 million tonnes of crude oil a year. The complex would also contain a 1.5-million-tonne-a-year mixed-feed ethylene cracker and downstream units. A cracker converts its feed into building blocks such as ethylene that can go into plastics and other chemicals. BPCL calls 10.5 million tonnes the combined throughput of the complex, not its crude refining capacity.

BPCL reported 35.3 million tonnes a year of existing refining capacity in the filing, with utilisation of 116.6% in FY 2025–26. Against that stated capacity, an additional 9 million tonnes would be about a quarter more crude capacity, if the new refinery comes on stream. The high utilisation figure describes BPCL’s own refineries against their rated capacity. It is not evidence of a nationwide fuel shortage.

The Crunch

The board decision moves Ramayapatnam beyond pre-project work, but the next things to watch are the outstanding approvals and the terms on which the subsidiary raises money. Those decisions will tell us more about what the project can build, at what cost and on what schedule.