Kheria’s MG Hector Tomahawk supply order shows how an electric or hybrid vehicle programme can drive investment outside the powertrain.

Why does a car door need a ₹5 crore machine? Kheria is adding a moulding machine to make trim for the Hector Tomahawk.

When a carmaker offers the same SUV as a battery EV and a plug-in hybrid, the powertrains are different. But suppliers outside the powertrain can sometimes serve both. A new order for the MG Hector Tomahawk offers a concrete example: a Gujarat supplier is buying a machine to make parts for the inside of its doors.

Who placed the order?

Kheria Autocomp told the stock exchange on November 26 that it had secured an order worth about ₹12 crore annually for door-trim components for the battery-electric and plug-in hybrid programme. The customer is Yanfeng India Automotive Interior Systems, not MG directly. Kheria makes moulded components for a supplier that serves the carmaker.

Kheria says it has placed an order for an additional 1,700-tonne injection-moulding machine at an estimated cost of ₹5 crore. It expects the machine to be operational by April 2027 and plans to fund it with remaining IPO proceeds and money generated by the business.

What does 1,700 tonnes mean here?

The rating describes the force the machine can use to hold the two halves of a mould closed while molten plastic is injected. It is not the machine’s weight or how much plastic it processes. A part that covers a larger area can require more clamping force because the plastic pushes against more of the mould. The shape of the part, the material and the pressure also matter.

What would make the investment pay off?

The ₹12 crore figure is the stated annual value of the programme, not profit or revenue already earned. Comparing it with the ₹5 crore machine budget does not tell you how quickly the investment will pay back. You would need to know how many parts the customer calls for, how much it costs to make them, and how much of the machine’s time is actually used.

The useful distinction is between winning a programme and getting a factory ready to supply it. Kheria says it has done the first and ordered the equipment for the second. The next milestone is getting the machine into operation.