India’s Ministry of Coal opened 85 bids on 20 November covering 18 of the 26 commercial coal blocks on offer. The bids show where companies are interested in mining, but no block has been awarded on the strength of this opening.
Interest was spread unevenly
The 16th round drew 83 bids for 17 blocks. A second attempt under the 15th round added two bids for one block. Across the combined offering, 16 blocks attracted more than one bid. Two received one apiece and eight received none. The ministry also counted 20 first-time bidders. The 85 bids are submissions, not 85 separate companies.
What happens after bids are opened
A technical committee will review the submissions. Only bidders that qualify move through to the electronic auction. An auction result is another milestone, not mine output: a winning bidder still has to develop the site and obtain the permissions needed to start mining.
The difference matters when reading coal supply figures. The ministry reported 210.46 million tonnes of output from captive and commercial mines combined in FY2025–26. That was production from existing operations, not a forecast for the blocks now in bidding. Captive and commercial supply should not be treated as the same category.
Read more on how coal stocks buffer India’s electricity supply.






Leave your thoughts