Maruti Suzuki sold nearly 19.7 lakh vehicles in the financial year that ended in March 2023, up 19% from the previous year. In the same year, it said shortages of electronic components kept it from building about 1.7 lakh vehicles. The company sold more than before, but it still built fewer vehicles than it estimated it could have with enough parts.

This edition of Makhanas Unpacked uses Maruti’s results to explain how a shortage can limit production even when sales rise. The Goal, the management novel by Eliyahu M. Goldratt and Jeff Cox, helps explain why an extra shift would not fix a parts shortage. That is a way to read the case, not a claim that Maruti followed the book.
A factory can have room to build more and still run out of parts
In FY2021–22, Maruti estimated that electronic component shortages affected production of about 2.7 lakh vehicles. In FY2022–23, it reported a production shortfall of about 1.7 lakh for the same reason. The estimates describe what the company could not build, not how many sales disappeared or how many customers were waiting. Annual sales include both domestic sales and exports.

In the novel, plant manager Alex Rogo learns to look for the constraint that limits what the whole operation can deliver. A bottleneck can be a machine on the factory floor. It can also be a part that never arrives at the gate. Improving a step that already has spare capacity doesn’t necessarily change what leaves the factory.

Would an extra shift or more parts help the factory finish more units?
Imagine a factory that can assemble 100 identical units this week but has only 70 approved control modules. Each finished unit needs one module. There are enough orders and every other input is available. The factory can add assembly time for 20 more units or get 20 more compatible modules.

An extra shift leaves output at 70 because the factory still has only 70 modules. The 20 extra modules let it finish 90, within its current assembly capacity. If it gets to 100 modules, assembly capacity may become the next limit. This is an illustration, not a reconstruction of Maruti’s production line.



Find what stops the next finished unit

In its FY2024–25 report, Maruti said planning, regular conversations with suppliers and developing alternative sources helped it improve the availability of electronic components. It did not isolate the effect of any one measure. The later report is not proof of what drove the fall in the earlier shortfall.
The same rule applies outside manufacturing. A service team can prepare more files without closing an extra case if they all wait for the same final approval. Before hiring or adding capacity, count what the operation can finish with the inputs it has. Then ask what would let it finish one more.

Read next: How a parts supplier is planning capacity for Maruti’s Kharkhoda factory.