Maruti sold more vehicles even as a parts shortage left about 1.7 lakh unbuilt

3 minutes

Maruti’s FY2022–23 results illustrate a lesson from The Goal: adding assembly time does little when an essential part limits how much the factory can finish.

Conceptual vehicle outline with an empty module position, illustrating how a missing part can stop assembly.

Maruti Suzuki sold nearly 19.7 lakh vehicles in the financial year that ended in March 2023, up 19% from the previous year. In the same year, it said shortages of electronic components kept it from building about 1.7 lakh vehicles. The company sold more than before, but it still built fewer vehicles than it estimated it could have with enough parts.

Maruti sold about 1.97 million vehicles in FY2022–23, up 19%, and reported missing about 170,000 vehicles of production.
Maruti’s sales and its reported production shortfall are different figures.

This edition of Makhanas Unpacked uses Maruti’s results to explain how a shortage can limit production even when sales rise. The Goal, the management novel by Eliyahu M. Goldratt and Jeff Cox, helps explain why an extra shift would not fix a parts shortage. That is a way to read the case, not a claim that Maruti followed the book.

A factory can have room to build more and still run out of parts

In FY2021–22, Maruti estimated that electronic component shortages affected production of about 2.7 lakh vehicles. In FY2022–23, it reported a production shortfall of about 1.7 lakh for the same reason. The estimates describe what the company could not build, not how many sales disappeared or how many customers were waiting. Annual sales include both domestic sales and exports.

Company estimates: about 270,000 vehicles affected in FY2021–22 and about 170,000 in FY2022–23. These are not lost sales.
Both numbers are company estimates of production affected by shortages, not estimates of lost sales.

In the novel, plant manager Alex Rogo learns to look for the constraint that limits what the whole operation can deliver. A bottleneck can be a machine on the factory floor. It can also be a part that never arrives at the gate. Improving a step that already has spare capacity doesn’t necessarily change what leaves the factory.

A component can limit how many vehicles are finished even if the factory has spare assembly time.
The illustration shows why assembly capacity is not always the binding constraint.

Would an extra shift or more parts help the factory finish more units?

Imagine a factory that can assemble 100 identical units this week but has only 70 approved control modules. Each finished unit needs one module. There are enough orders and every other input is available. The factory can add assembly time for 20 more units or get 20 more compatible modules.

Illustration: the line can assemble 100 units but has only 70 approved modules. Which change would help?
Assume enough orders and all other inputs. Each finished unit needs one approved module.

An extra shift leaves output at 70 because the factory still has only 70 modules. The 20 extra modules let it finish 90, within its current assembly capacity. If it gets to 100 modules, assembly capacity may become the next limit. This is an illustration, not a reconstruction of Maruti’s production line.

Illustration: increase assembly capacity to 120 and keep 70 modules, and the line still finishes 70 units.
More assembly time cannot replace a missing module.
Illustration: keep assembly capacity at 100 and increase approved modules to 90, and the line finishes 90 units.
More modules help while the line has room to assemble them.
Illustration: at 100 modules and assembly capacity of 100, the line can become the next limit.
The constraint can move once the supply of modules improves.

Find what stops the next finished unit

The Goal by Eliyahu M. Goldratt and Jeff Cox explains bottlenecks; it does not establish what Maruti read.
The novel offers a way to read the example, not evidence about Maruti’s reading.

In its FY2024–25 report, Maruti said planning, regular conversations with suppliers and developing alternative sources helped it improve the availability of electronic components. It did not isolate the effect of any one measure. The later report is not proof of what drove the fall in the earlier shortfall.

The same rule applies outside manufacturing. A service team can prepare more files without closing an extra case if they all wait for the same final approval. Before hiring or adding capacity, count what the operation can finish with the inputs it has. Then ask what would let it finish one more.

Three questions: What comes in? What can you finish? What stops the next one?
Ask these questions before adding another shift or another person.